Penhorwood Demolition Schedule

Help: Mouse over timelines for work details.

 

Key map of demolition site

Notes

This schedule is tentative and weather dependent. Certain weather conditions are required throughout the demolition process. Any changes to the schedule will be posted here.

Change Log

Jan. 15: Estimated demolition time for each building reduced to two days, from three. Project end date changed to Feb. 1, from Feb. 18.

Jan. 30: Removal of Building F debris expected to be complete Jan. 31. Crew will have scheduled days off beginning Feb. 2 and will be back on site Feb. 9. Project end now estimated to be Feb. 12.

Feb. 13: Final safety inspection will be Feb. 17. Last day on the site now set at Feb. 18.