Penhorwood Demolition Updates

Entry Time Span: All ( 5 posts )
 
 
 

Weather conditions have been favourable for the demolition and debris removal processes. Demolition has finished on schedule, though the completion date for debris removal and demobilization has been extended until Feb. 18. Details can be found on the demolition schedule. Starting Feb. 2, crews had seven scheduled days off, and resumed work on Feb. 9 Crews continue to remove concrete and metal from the site. Once the site has been cleared, open areas will be backfilled and levelled, followed by demobilization. A final safety inspection of the site is scheduled for Feb. 17 to ensure there are no hazards remain following the demolition and clean-up process. The revised end date is now Feb. 18. All timelines are subject to weather ...

Read More >>

Current weather conditions are favourable for the demolition and debris removal processes. Demolition was finished on schedule though the completion date for debris removal and demobilization has been extended until Feb. 12. Details can be found on the demolition schedule. The demolition process was finished on Jan. 28, on time and on schedule. At this stage, crews are still removing debris from the site. Demolition of Building E began on Jan. 25 and was completed on Jan. 26, while demolition for Building F began on Jan. 27 and was completed on Jan 28. This concluded the demolition process for all seven buildings. Operations ran smoothly and the demolition process took two days per building. Crews began removing debris from Building ...

Read More >>

The current weather conditions are favourable for the demolition. All processes are on schedule with an expected completion date of Feb. 1. Demolition of Building D began on Jan. 19 and was completed on Jan. 20, while demolition for Building B began on Jan. 21 and was completed on Jan 22. Crews are scheduled to begin demolition of Building C on Jan. 23 and Building E on Jan 25. Operations continue to run smoothly therefore the demolition process is still scheduled to take two days per building. Regional Emergency Services continues to conduct safety checks before crews begin demolishing each building to ensure hazards do not arise during the process. Crews finished removing debris from Buildings G and A on ...

Read More >>

Current weather conditions are favourable for the demolition and all processes are on schedule. Based on progress made, the contractor has modified the schedule to reflect a two-day demolition process for each building rather than four days, shortening the overall timelines originally anticipated for the demolition. The original timeline outlined a finish date of Feb. 18, but with the shorter demolition times, the project is now scheduled to be complete by Feb. 1. Envirocon, the contractor for the project, began site setup and mobilization early in the week and completed on Jan. 14. In addition, hazardous materials abatement was completed on Jan. 14. Demolition of Buildings A and G began on Jan. 15 as scheduled. Before the demolition began on ...

Read More >>

The following letter was delivered to Penhorwood condominium owners the week of December 1, 2014. Additional information related to the demolition of the Penhorwood buildings will be made available on December 15. We encourage you to check back at this time for more information. Invitation to an information session on the Penhorwood Demolition Process Dear Owner, On behalf of the Regional Municipality of Wood Buffalo, I am writing to let you know about the next steps in the demolition process of the Penhorwood condominiums. On November 25, Mayor and Council passed a resolution approving the funding of the demolition of the Penhorwood condominiums. As a result of this decision, we’re inviting you to an information session to share information about ...

Read More >>