Clearwater Drive Construction

Download

PLB Phases Thumbnail

[Click image for enlarged view]

Construction of Clearwater Dr. (formerly known as Prairie Loop Blvd.) will be completed in phases, beginning in May 2017. When complete, the road will run from the southeast end of Franklin Ave. to Morrison St.

Notice: Hardin St. Reopened

As of November 1st, the intersection at Hardin Street and Clearwater Drive (formerly Prairie Loop Blvd.) will open to traffic.

Please be advised that sidewalks in the area are still under construction and will not be available for pedestrian access until further notice. Please observe any posted signage.

Phase 4 Construction - Hardin St. to Morrison St.

The Regional Municipality of Wood Buffalo is initializing construction of Clearwater Drive (formerly known as Prairie Loop Blvd.) from Hardin Street to Morrison Street.

The Scope of this project will affect residents and traffic on Gordon Ave, Main Street, and Morrison Street. Construction activities are expected from September 1 2017 to November 15, 2017 and then April 15, 2018 through November 15, 2018.

Access to Snye Park, to the Amenities Building, and to all residents will be maintained through the course of this project.

Prairie Loop Phase 4 Map

E Construction has been selected as the General Contractor for this project and will be responsible for the planning, safety and traffic management associated with construction activities.

If you have questions, please visit rmwb.ca/Construction or contact the Construction Hotline at 780-793-1054 or constructionhelpdesk@rmwb.ca.