Is it safe to say spring has sprung? We hope so, as it kicks off our busy construction season of 2025! We are pleased to share the following information with you, as we continue to support our community and be of assistance to you.
Electrical Updates |
The Season is Changing
As the days are getting longer, the temperatures are increasing, and the snow is melting, we are moving into a new season. Here are some things to keep in mind from an electrical safety aspect:
Fire Alarms Who can install, verify, inspect, test and maintain a fire alarm system? Alberta Municipal Affairs recently released a joint Building/Fire/Electrical interpretation on this topic found here. There are five types of activities conducted on an fire alarm system:
1. Installation - includes a new install or additions, modifications, and renovations (changes) to an existing installation. 2. Verification - involves inspection and testing for verifying the FAS conforms to the design, and applicable codes and standards, and performs all its intended functions. 3. Inspection - a visual examination to determine the device or system will apparently perform in accordance with its intended function. 4. Testing - the operation of a device or system to determine it will perform in accordance with its intended operation or function. 5. Maintenance - the removal, replacement, or servicing of devices or equipment found inoperative during an inspection and testing of the fire alarm system.
This would include the discovery of an inoperative device at any other time outside of the scheduled mandatory inspections. These 5 requirements for fire alarm and voice communication systems can only be completed by those recognized as qualified to do so under Division C of the National Fire Code (Alberta Edition).
Important Information Those persons who have Fire Alarm Technician certification from the Northern Alberta Institute of Technology or Southern Alberta Institute of Technology are still qualified to inspect, test and maintain fire alarm and voice communication systems until December 31, 2025. To continue to inspect, test and maintain these systems after this date, persons must obtain a certificate of training from the CFAA. Prior to 2000, Alberta Labour issued a “P” ticket number or a personal identification number (PIN) card to certified electricians, manufacturer-trained technicians, electronics technicians, electrical engineering technologists, and professional electrical engineers. This P card was to confirm that the individual had successfully passed their training to conduct work on fire alarm systems. In 2000, the practice of issuing a P ticket or PIN was discontinued. As Alberta Municipal Affairs no longer has the Alberta Labour program in place, the confirmation of a P ticket or PIN can no longer be provided. Anyone still in possession of their laminated P card should note that the card is still valid until December 31, 2025. Cards issued by the Alberta Fire Safety Association (AFSA) will no longer be recognized as proof of certification effective December 31, 2025.
Solar Photovoltaic Installations Solar Photovoltaic (PV) systems on residential properties is becoming increasingly popular in our region. There are many Canadian Electrical Code rules to be followed for such installations, most notably, sections 64 and 84. RMWB Safety Codes has a guideline to help navigate your way through the permitting process and explains what is required.
ONE FINAL NOTE: THE 2024 CANADIAN ELECTRICAL CODE COMES INTO EFFECT IN ALBERTA ON APRIL 1, 2025. Any electrical permits issued after this date will be subject to code enforcement of the new edition.
|
Plumbing and Gas Updates |
Spring Is in The Air
It’s been a long winter, but spring is coming. This means a change in the type of work we’re doing; usually, it means there’s a lot more digging.
Plumbing Groundworks are going to be a regular occurrence. Here are some helpful reminders:
Gas As the frost comes out of the ground, we become much more aware of the role played by swing joints and exterior vertical supports where the line enters the building. These requirements can be found in the B149.1:20 under clause 6.16 (Protection of Piping). We need to be sure that any underground piping is done according to Clauses 6.2.8 (soft copper requirements) and the entirety of 6.15 (Underground piping).
A quick side note: the 2025 gas code has been released and is available online for purchase at
And a final thought; please be safe in your excavations. Be mindful of the water seeping in through the sidewalls, pay attention to any cracks you see (they can tell a lot about the potential for sidewall collapse), and be mindful of the choices you make BEFORE you go into the hole. Always communicate with the excavator about the safety of the excavation; they are your subject matter experts. |
Building Updates |
New Barrier Free Accessibility Requirements / Additional Power Door Operator’s Required
There are several new barrier free accessibility requirements in the 2023 National Building Code/ Alberta Edition (NBC (AE)), that constructors, designers and business owners should be aware of. The Codes for accessibility design requirements exist to allow for the proper and safe access and use of the built environment. Designers and builders must demonstrate compliance with the NBC(AE) at the permit application stage in their design prior construction. This helps avoid costly rework and errors. The Codes for accessible design exist to regulate a proper and safe outcome for people of all ages and abilities. Section 3.8. Accessibility in the NBC(AE) sets forth the technical requirements for accessibility in design. Section 3.8. and other applicable Codes apply to all new construction, additions to existing buildings, changes to existing buildings and changes in use. Below are the new requirements and additional locations for power door operators.
3.8.2.7. Power Door Operators 1) Doors shall be equipped with power door operators complying with Subsection 3.8.3. that allows persons to activate the opening of the doors in the intended direction of travel, where the doors are located a) in a pedestrian entrance including the interior doors of a vestibule where provided, b) in a barrier-free path of travel, between the entrance and the entrance doors to suites or rooms served by a public corridor or a corridor used by the public), and c) in an entrance to a washroom with a barrier-free water closet.
3.8.5.2. Physician Clinics and Offices 2) Every door that is in a barrier-free path of travel to a physician clinic or office shall be equipped with a power door operator that complies with Subsection 3.8.3. and allows persons to activate the opening of the door in the intended direction of travel.
3.8.3.6.(11) Clearance at Doorways / Hallways and Corridors 11) Unless equipped with a power door operator complying with Sentence (6), a swinging door in a barrier-free path of travel shall have a clear space on the latch side extending the height of the doorway and not less than a) 600 mm beyond the edge of the door opening if the door swings toward the approach side, and b) 300 mm beyond the edge of the door opening if the door swings away from the approach side.
7) A cane-detectable guard shall be installed on the hinged side of power-assisted doors that swing open into the path of travel. For more information on Accessibility Design Code requirements, the Alberta Safety Code Council has released the 2024 version of the Accessibility Design. Full of illustrations and in-depth explanations of the codes requirements it is an invaluable design tool for anyone needing to design for accessibility. It can be found here: Accessibility Design Code Requirements |
The Safety Codes Department is committed to supporting safe work across our region. If you have questions or concerns, please contact us at the phone or email address above. We are always happy to help!