Fort McKay Range Road 1109 and South Waterline & Sidewalk Improvement
Introduction:
Consun Contracting will be completing Fort McKay Range Road 1109 and the south waterline and sidewalk improvement in your neighbourhood.
Background:
This project is expected to resume after April 15th, 2026. Activities include road markings, sidewalk construction and landscaping from the intersection towards the new Community Centre.
Work will continue from the intersection of RR1109 and Fort McKay Road to the Fort McKay River bridge. This scope also includes sidewalk, beautification, upgrading of the watermain and storm drainage.
Please see the maps below for construction areas:


Proposed Start and End Dates:
South waterline and sidewalk improvement is expected to start on April 15th, 2026 and be substantially completed by August 15th, 2026.
Contractor:
Consun Contracting
Lead Department:
Project Management Office
Community Benefit:
The community will have new pedestrian connectivity from the Fort McKay River bridge north to the Community Centre and community. The Range Road 1109 will be upgraded to current standards, with underground utilities that will provide service for the Community Centre. The existing water line servicing the south portion of the Community will be replaced with a larger main to improve service.
Construction Impacts:
☒Temporary Water/Sewer
☒Road or Lane Closure
Special Instructions for Residents:
Temporary water:
Temporary water bypass will be set up from May 1, 2026- August 15, 2026
The contractor will be upgrading the existing watermain along Fort McKay Road. To complete this work it will be required to shut down the water main for the duration of construction. Temporary water will be provided to ensure safe drinking water remains available to residents and businesses.
The contractor’s plumber, Ram Mechanical, will be required to enter each residence and business. They will be checking the existing water service to ensure there are no leaks. Modifications may be required to connect the temporary water.
Once temporary water has been connected it is recommended to run a tap for approximately 5 minutes. This will allow water to flush through the system to the property and ensure no interruption in service.
Road or lane closure
Fort McKay Rd will have single lane traffic during construction hours. There will be only occasional construction delays on Range Road 1109.
For more information, please contact Pulse at 780-743-7000 or 1-800-973-9663. You can also visit rmwb.ca/construction and subscribe for updates directly to your inbox.