Gregoire Skate Park Development
Introduction:
The skatepark development project at Greely Road in Gregoire, involves the construction of a concrete slab, installation of modular skate components, and landscaping surrounding the skatepark.
The project began in 2025; however, inspection determined that the concrete slab did not meet the required quality standards. As a result, the contractor, Canadian Ramp Company, has been instructed to reconstruct the slab this construction season.
Map:

Map of construction zone
Proposed Start and End Dates:
April 20, 2026-July 31, 2026
Contractor:
Canadian Ramp Company (Prime), Green Construction (Sub Contractor)
Lead Department:
Project Management Office
Project Details:
The removal of the existing skate features is scheduled for the week of April 20. This will be followed by slab demolition and reconstruction, which are anticipated to take place between the third week of May 19 and June 1, 2026.
Completion of the slab construction and reinstallation of the skate features is expected to be completed by June 30, 2026. The landscaping activities surrounding the skatepark will begin after construction ends and are expected to take approximately two weeks.
Community Benefit:
Residents will have the opportunity to enjoy the improved surface designed for skatepark activities.
Construction Impacts:
☒Parking & Vehicle Access
A section of the parking lot has been assigned to the contractor for a laydown area.
Special Instructions for Residents:
Residents are advised to watch for construction signage and stay away from the construction site until the skatepark is officially opened for public use.
For more information, please contact Pulse at 780-743-7000 or 1-800-973-9663. You can also visit rmwb.ca/construction and subscribe for updates directly to your inbox.