Road Surface and Alleyways Improvements: Wood Buffalo Way
Introduction:
The Regional Municipality of Wood Buffalo is preparing to complete additional drainage improvements in your neighborhood. The disrupted areas are being kept to a minimum and no significant impact to traffic should be anticipated. The trail located northeast of Wood Buffalo Way will be temporarily closed while the work is taking place.
Map:
The above highlighted area shows the project footprint and what will be affected during construction.
Proposed Start and End Dates:
September 17, 2025 – September 27,2025
Contractor:
H. Wilson Industries Ltd.
Lead Department:
Project Management Office
Project Details:
Project scope will include the installation of the catch basin and culvert leads to improve the outfall drainage. Area and the trail to be landscaped and restored. The crews will ensure access to and from properties is maintained and available to all the residents impacted by construction.
Community Benefit:
As the various phases of construction are completed, affected portions of Wood Buffalo Way will be restored and improved. At the completion of the project, the impacted portion(s) of the road will see a substantial improvement, aligning with the Municipality’s commitment to infrastructure improvements.
Construction Impacts:
☐Temporary Water/Sewer
☐Parking & Vehicle Access
☐Garbage Pick Up
☐Driveway Interruption
☒Sidewalk Closure
☐Mailbox Relocation
☒Road or Lane Closure
☐Laydown Yard
☐Transit
☐Other
Services such as garbage pickup and Emergency Services will not be interrupted and appropriate access will be maintained at all times.
Notice for residents:
All dates and timelines outlined above are approximations of when the work may be taking place in this area. Access to the work area may be required throughout the project area at any time. H. Wilson will adhere to applicable noise and disturbance bylaws. Timelines are subject to change based on weather, equipment, and other unforeseen factors.
For more information, please contact Pulse at 780-743-7000 or 1-800-973-9663. You can also visit rmwb.ca/construction and subscribe for updates directly to your inbox.
Contact Us
PULSE
Submit a request
Phone: 780-743-7000
Toll free: 1-800-973-9663
Subscribe for RMWB updates
Stay up to date on the services, programs and projects in your neighbourhood!