St. Martha’s School Playground Replacement

Introduction:

St. Martha's School playground was identified to be replaced as it is at the end of its' life cycle. Construction started August 11, 2025.

 Image:

Construction work zone.

Proposed Start and End Dates:

August 11, 2025-September 30, 2025

Contractor:

Habitat Systems Inc.

Lead Department:

Project Management Office

Project Details:

Playground equipment as identified in the photo will be replaced over the next six weeks.

Community Benefit:

The new equipment will provide a safe outdoor play space for families and children.

Construction Impacts:

☐Temporary Water/Sewer

☒Parking & Vehicle Access

☐Garbage Pick Up

☐Driveway Interruption

☐Sidewalk Closure

☐Mailbox Relocation

☐Road or Lane Closure

☐Laydown Yard

☐Transit

☐Other

Special Instructions for Residents:

The contractor will be using the parking lot for access to the construction site. The playground is closed until the project is completed at the end of September.

Residents are advised to stay away from the work site.

For more information, please contact Pulse at 780-743-7000 or 1-800-973-9663. You can also visit rmwb.ca/construction and subscribe for updates directly to your inbox.

 