Jerry Cooper Outdoor Rink Surface Upgrade
Introduction:
The project primarily consists of replacing the existing asphalt surface with a reinforced concrete surface, constructing a player's box, adding a basketball facility, upgrading the rink components and maintenance ramp.
Map:

Proposed Start and End Dates:
August 31, 2026- December 31, 2026
Contractor:
GLV Construction
Lead Department:
Project Management Office
Project Details:
The project is scheduled to mobilize on August 31, 2026. Substantial completion is anticipated by the end of December 2026, with landscaping and final site cleanup to be completed the following spring.
Community Benefit:
The community will have access to an enhanced playing surface, as well as player's box that provides shelter.
Construction Impacts:
No impact on parking lot as a separate laydown area has been designated for the contractor, shown in the site drawings.
Special Instructions for Residents:
Residents are advised to exercise caution and take appropriate precautions around the construction zone.
For more information, please contact Pulse at 780-743-7000 or 1-800-973-9663. You can also visit rmwb.ca/construction and subscribe for updates directly to your inbox.
Subscribe for RMWB updates
Stay up to date on the services, programs and projects in your neighbourhood!